General Electric

Owensboro, KY

General Electric tasked Klenck Company with the removal of un-auctioned machinery and the remaining MEP once the Owensboro plant had shut down. The large interior space allowed for our Fuchs 350 wheeled excavator and steel shear to be taken from the scrap yard and employed onsite. Once the larger steel was processed, a Cat 308 mini-excavator equipped with a steel shear began cutting small ferrous and larger nonferrous materials to recycle. By utilizing shears instead of torches, hazardous fumes were minimized and overall site safety was improved. This project employed nearly thirty individuals working seven, 12 hour days for a three month period in an interior space with zero personnel safety incidents on time and within contract.